Estimating: early-stage estimates

Conceptual estimate: methods, accuracy and uses

A conceptual estimate prices a project before meaningful design exists. It is a screening number with a stated range, not a bid.

Short answer

A conceptual estimate is an early cost estimate prepared from a program, sketch or site plan before design is developed. Owners and contractors use it to decide whether a project is worth pursuing. Under the AACE classification most cost engineers cite, it is usually a Class 5 or Class 4 estimate with a wide accuracy range.

Want the conceptual budget done for you? Multi-trade estimates from $1,150, with the delivery date set in your quote. Fixed quote within 2 business hours, and you pay only after you accept. See conceptual budget and ROM estimates.

Get a fixed quote

What a conceptual estimate is for

A conceptual estimate answers one question: is this project roughly affordable? Owners use it to screen sites, size programs and decide whether to fund design.

Contractors are asked for one in preconstruction, often with a program, a site and a target square footage. It is not a bid and should never be presented as one. Label it as conceptual every time it leaves your desk, with its class and range.

How accurate is a conceptual estimate?

Less accurate than most people expect. The US Department of Energy summarizes AACE International Recommended Practice 18R-97, which classes estimates by how much of the project is defined. The ranges are for process industries; AACE publishes a separate practice for building and general construction, 56R-08.

Class Project definition Typical use Expected accuracy (80% confidence)
Class 5 0% to 2% Concept screening Low -20% to -50%, high +30% to +100%
Class 4 1% to 15% Study or feasibility Low -15% to -30%, high +20% to +50%
Class 3 10% to 40% Budget authorization Low -10% to -20%, high +10% to +30%

A conceptual estimate is usually Class 5 or Class 4. On a Class 4 number, the final cost could reasonably land 30% below or 50% above it. That reflects how little is defined, not a bad estimator.

Conceptual estimate vs budget estimate vs bid estimate

The difference is how much design exists and what the number is used for.

  • Conceptual estimate: from a program or concept sketch. Decides whether to pursue the project.
  • Budget estimate: from schematic or early design development drawings. Sets the funded budget, often around Class 3.
  • Bid estimate: from construction documents with measured quantities and sub quotes. Becomes a price someone is held to.

See types of construction estimates for the full sequence.

Short on time? Bidmere can do this for you. Trade estimates from $195, ready in 48 hours. See rough order of magnitude and budget estimates or get a fixed quote.

Three ways to build a conceptual estimate

Most estimators combine methods: a square foot check plus a systems estimate for the real number.

  1. Square foot or unit cost. Multiply gross area by a cost per square foot from comparable projects or a published cost database. Adjust for location, building type, quality and the date of the data.
  2. Assembly or systems cost. Price foundations, structure, envelope, roofing, interiors, MEP and sitework separately, each with a unit such as wall area or roof area. Slower, but it shows the owner where the money goes.
  3. Capacity or parametric factoring. Common in industrial work. Scale from a known project by capacity, such as beds, parking spaces or gallons per day. Cost rarely rises one to one with size.

What a conceptual estimate should include

A conceptual number without its basis gets copied into board decks as if it were a bid. Write these down with it:

  • Basis of estimate: what documents existed, what you assumed, and the cost data source and date.
  • Scope boundaries: land, design fees, furniture and equipment, permits, utility fees and owner contingency, each marked in or out.
  • Location and escalation: a location factor, and escalation to the midpoint of construction, not today.
  • Markups: general conditions, overhead, profit, bonds and insurance as separate lines.
  • Design contingency: for scope that will appear as design develops.
  • Class and range: the estimate class and its low and high range.

Common conceptual estimate mistakes

These errors move early numbers more than the method does:

  • Using cost data from another region or year without adjusting it.
  • Leaving out sitework and utilities, which can swing early numbers more than the building.
  • Treating contingency as padding to remove later instead of the price of undefined scope.
  • Presenting one number with no range.
  • Skipping escalation on a project that will not start for two years.

When to get help with a conceptual estimate

If a conceptual number will drive a go or no-go decision, a financing request or a GMP conversation, it deserves documentation like a bid. Bidmere prepares budget and conceptual estimates with a written basis of estimate and stated range, at your rates where you have them. Send what you have: a program, sketches or a site plan. You get a fixed price and delivery date within 2 business hours, and pay only after you accept.

Frequently asked questions

Is a conceptual estimate the same as a rough order of magnitude (ROM)?

In practice, mostly yes. Both describe early, low-definition estimates with wide ranges. ROM is common in government and IT work, and conceptual is more common in building construction. Whatever you call it, state the estimate class, the documents it used and the range.

How long does a conceptual estimate take?

Hours to a few days, depending on the method. A square foot screen is fast. A systems estimate for a complex building takes longer because each system is priced separately. Bidmere gives a fixed delivery date with the quote, within 2 business hours of your request.

Should a conceptual estimate include contingency?

Yes. Design contingency covers scope that will appear as the design develops, and it is not optional at this stage. Show it as its own line so the owner can see it shrink as the design matures, instead of hiding it inside unit costs.

What accuracy should I put on a conceptual estimate?

Use the class that matches how much is defined. The DOE summary of AACE 18R-97 gives Class 5 a range of -20% to -50% low and +30% to +100% high, and Class 4 -15% to -30% low and +20% to +50% high. Those ranges are for process industries.

Can I get a conceptual estimate from a site plan only?

Yes, if the program is clear: building type, approximate area, quality level and location. The estimate will be a screening number with a wide range. The more you can send, such as massing sketches or an outline spec, the narrower the range can be.

What does a Bidmere conceptual estimate cost?

Budget and conceptual estimates are quoted to scope. Single-trade estimates are priced from $195 and multi-trade estimates from $1,150. You get a fixed price within 2 business hours, plan review is free, and you pay only after you accept the price and delivery date.

Get a fixed quote

Share the project basics. You get a fixed price and delivery date within 2 business hours. Plan review is free, and you pay only after you accept.

A sentence or two is enough. Leave private rates out of this box.
Add details (optional)
Share a view-only link if you have one. It lets us quote faster; you can also send documents after we reply.
Prefer a call? Leave a number and a time
Optional. We still reply by email, and call only if you ask here.

Preparing the form…

* Required. We reply by email within 2 business hours. Plan review and quotes are free.

Need it done? Fixed price in 2 hoursGet a quote